The Cabinet Committee on Economic Affairs chaired by Hon’ble Prime Minister Shri Narendra Modi has approved the investment for 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Limited, for an estimated cost of Rs. 2614.51 crore including Rs. 13.80 crore as budgetary support from Government of India for cost of enabling infrastructure. Ex-post facto approval is given for cumulative expenditure incurred amounting to Rs.246 crore till January, 2022.

Project cost of Rs.2614 crore included hard cost amounting to Rs.2246.40 crore, Interest During Construction (IDC) and Financing Charges (FC) of Rs. 358.96 crore & 9.15 crore respectively. The revised cost sanctions for cost variations due to quantity changes (including additions/ alterations/ extra items) and time overruns due to the developer shall be capped at 10% of sanctioned cost.

Keeping in view the aims and objectives of Atmanirbhar Bharat Abhiyan, the present proposal for setting up of 382 MW Sunni Dam HEP by SJVN shall provide various benefits to local suppliers/ local enterprises/ MSMEs and shall encourage entrepreneurship opportunities within the country besides promoting employment and socio-economic development of the region. The implementation of the project shall generate direct & indirect employment to about 4000 persons during peak construction of the project.

Explore More
140 crore Indians have taken a collective resolve to build a Viksit Bharat: PM Modi on Independence Day

Popular Speeches

140 crore Indians have taken a collective resolve to build a Viksit Bharat: PM Modi on Independence Day
Double engine govt becoming symbol of good governance, says PM Modi

Media Coverage

Double engine govt becoming symbol of good governance, says PM Modi
NM on the go

Nm on the go

Always be the first to hear from the PM. Get the App Now!
...
Social Media Corner 17th December 2024
December 17, 2024

Unstoppable Progress: India Continues to Grow Across Diverse Sectors with the Modi Government