The Cabinet Committee on Economic Affairs, chaired by the Hon’ble Prime Minister, Shri Narendra Modi, today approved the project on Green Energy Corridor (GEC) Phase-II – Inter-State Transmission System (ISTS) for 13 GW Renewable Energy Project in Ladakh.

The project is targeted to be set up by FY 2029-30 with total estimated cost of Rs.20,773.70 crore and Central Financial Assistance (CFA) @ 40 percent of the project cost i.e. Rs.8,309.48 crore.

Keeping in view the complex terrain, adverse climatic conditions and defence sensitivities of Ladakh region, Power Grid Corporation of India Limited (POWERGRID) will be the Implementing Agency for this project. State of the art Voltage Source Converter (VSC) based High Voltage Direct Current (HVDC) system and Extra High Voltage Alternating Current (EHVAC) systems will be deployed.

The transmission line for evacuating this power will pass through Himachal Pradesh and Punjab up to Kaithal in Haryana, where it will be integrated with the National Grid. An interconnection is also planned from this project in Leh to existing Ladakh grid so as to ensure reliable power supply to the Ladakh. It will also be connected to Leh-Alusteng-Srinagar line to provide power to Jammu & Kashmir. The project will entail setting up of 713 km transmission lines (including 480 km HVDC line) and 5 GW capacity of HVDC terminal each at Pang (Ladakh) and Kaithal (Haryana).

The project will contribute to achieving the target of 500 GW of installed electricity capacity from non-fossil fuels by year 2030. The project will also help in developing long term energy security of the country and promote ecologically sustainable growth by reducing carbon footprint. It will generate large direct & indirect employment opportunities for both skilled and unskilled personnel in power and other related sectors, especially in Ladakh region.

This project is in addition to Intra-State Transmission System Green Energy Corridor Phase-II (InSTS GEC-II), which is already under implementation in the States of Gujarat, Himachal Pradesh, Karnataka, Kerala, Rajasthan, Tamil Nadu and Uttar Pradesh for grid integration and power evacuation of approx. 20 GW of RE power and is expected to be completed by 2026. The InSTS GEC-II scheme targets addition of 10753 ckm of transmission lines and 27546 MVA capacity of substations having estimated project cost of Rs.12,031.33 crore and CFA @33%, i.e. Rs.3970.34 crore.

Background:

The Prime Minister, during his Independence Day Speech on 15.08.2020, announced setting up of 7.5 GW Solar Park in Ladakh. After extensive field survey, the Ministry of New and Renewable Energy (MNRE) prepared a plan to set up 13 GW Renewable Energy (RE) generation capacity along with 12 GWh Battery Energy Storage System (BESS) in Pang, Ladakh. For evacuating this huge quantum of power, it will be necessary to create an inter-state transmission infrastructure.

  • Ram Kumar Singh October 20, 2023

    Modi hai to Mumkin hai
  • Kalyan Halder October 19, 2023

    good report
  • Bhagat Ram October 19, 2023

    karnatak abhi bahut piche chala gaya hai
  • vikas thakur October 19, 2023

    Modi sarkar bharat jindabad ji jai ho
  • Bhagat Ram October 19, 2023

    jisse apne vidhayak ko apne Kshetra mein jo jo karya ka Vada Kiya hai use pura karne mein asamarth ho raha hai अपने-अपने vidhayak ko Jaise fund mein van van karod account mein aata hai use mahila ke account mein 5000 aur 10 kg rice dene mein government Congress ka natak ka barbad kar Raha hai to Apne vidhayak ko Apne Kshetra ke karya mein Vada kya hai to Badnaam Ho Raha hai vah sab BJP ke party mein aana chahte Hain
  • Bhagat Ram October 19, 2023

    abhi karnatak m har mahila ko government ne 5000 hajar Dene ka wada Kiya hai Kendra government se 10kg rice adhik Dene ka wada Kiya hai
  • bhaskar sen October 19, 2023

    Corr: read : to perpetuate ...
  • bhaskar sen October 19, 2023

    cabinet committee of economic affairs under your guidance support and chairmanship did one of the most commendable jobs . May The Almighty bless you and your Government with continued instinct and power to continue with this synthesis of magnanimous mandates to take India to greater heights of glory . jai hind jai bharat 🙏
  • M.Gnanamoorthy October 19, 2023

    congratulations dynamic leader
  • Geeta Gupta October 19, 2023

    jai shree Ram jai bharat jai hind jai ho modi ji apki kripa ho to 7/7 2023 ko Geeta Gupta ke name se chithi likhi hu lockkalyan marg ke adress pr ek bar dekh lijiy please duniya keliy etna sb kuchh krte hai es garib nari ki baat to sunlijiy please 2015 se chithi likh rhi hu apne kisi adhikari se milwa dijiy please mera request hai please mera contact no. 9643361496 es pr massage
Explore More
Blood of every Indian is on the boil: PM Modi in Mann Ki Baat

Popular Speeches

Blood of every Indian is on the boil: PM Modi in Mann Ki Baat
India’s urban boom an oppurtunity to build sustainable cities: Former housing secretary

Media Coverage

India’s urban boom an oppurtunity to build sustainable cities: Former housing secretary
NM on the go

Nm on the go

Always be the first to hear from the PM. Get the App Now!
...
Social Media Corner 13th July 2025
July 13, 2025

From Spiritual Revival to Tech Independence India’s Transformation Under PM Modi